🦴 Sprint 9.4 · M20 Orthopaedics · Fracture AI + MSK Pathways · 11 - 31 Mar 2030
← Hub ← Phase 9 SPRINT 9.4 · v3.5 M20 ORTHO

Sprint 9.4 · M20 Orthopaedics · Fracture AI + MSK Pathways

M20 Orthopaedics — X-ray fracture AI · open fracture red-flag · MSK rehabilitation pathways. Specialist HITL with Orthopaedic Surgeon panel · validated clinical instruments · MOH CPG-aligned workflows · culturally adapted for ASEAN context.

1. 🎯 Sprint Summary

SprintSprint 9.4 · M20 Orthopaedics · Fracture AI + MSK Pathways
Duration11 - 31 Mar 2030
ModuleM20 Orthopaedics · Fracture AI + MSK Pathways · specialist HITL
GoalM20 production-certified · Orthopaedic Surgeon HITL panel ≥ 5 active · zero missed Open fracture red-flag
Capacity6 FTE + Founder 0.7 + Doc Zam 0.4 + Orthopaedic Surgeon Advisor (Datuk Dr Chandran Pillay) 0.5
Velocity92 SP
Demo31 Mar 2030

2. 🧩 Module Scope

  • X-ray fracture AI — image recognition · fracture vs no-fracture · multiple fractures
  • Open fracture red-flag — automated severity scoring · mandatory ortho surgeon escalation
  • MSK rehab pathways — physiotherapy protocols · post-op rehabilitation
  • Joint replacement long-term tracking — hip/knee replacement registry integration
  • Orthopaedic Surgeon specialist HITL · panel rota · SLA tracking
  • Open fracture red-flag workflow · mandatory specialist escalation
  • MOH CPG alignment · validated clinical instruments
  • Culturally adapted prompts (4 ASEAN contexts)
  • Cross-module care plan integration (chronic comorbidities)

3. 🚦 Pre-Sprint Gate

  • Sprint 9.3 closeout
  • Orthopaedic Surgeon advisor onboarded
  • Open fracture legal/clinical review complete
  • Orthopaedic Surgeon panel ≥ 5 specialists committed
  • MOH CPG sources licensed

4. 📅 Day-by-Day Plan

D1-3Mon-Wed · Kickoff + X-ray AI + MSK pathways
X-ray AI + MSK pathways integration · clinical workflow scoping.
D4-5Thu-Fri · Open fracture Red-Flag Workflow
Open fracture scoring · mandatory escalation logic.
D6Fri · Mid-Sprint Demo #1
Screening end-to-end · advisor review.
D7-8Mon-Tue · Specialist HITL + SLA
Orthopaedic Surgeon panel rota · SLA monitoring.
D9-10Wed-Thu · Cross-Module Care Plans
Composite care across specialties.
D11Fri · Mid-Sprint Demo #2
Full HITL workflow.
D12-13Mon-Tue · Cultural Prompts + CPG
4-culture prompt tuning · MOH CPG alignment.
D14Wed · Clinical Safety Audit
Orthopaedic Surgeon + Doc Zam clinical audit.
D15Thu-Fri · Stability + Production Test
Production load · 4-week stability run starts.
+Mon (next) · Sprint Demo + Retro
Orthopaedic Surgeon attestation · sprint demo · 9.5 prep.

5. 📦 Deliverables

FRItemSP
FR-9.4.1X-ray AI + MSK pathways validated instruments13
FR-9.4.2Open fracture red-flag workflow13
FR-9.4.3Orthopaedic Surgeon HITL panel + SLA13
FR-9.4.4MOH CPG alignment + validated workflows8
FR-9.4.5Culturally adapted prompts (4 ASEAN cultures)8
FR-9.4.6Cross-module care plan integration8
FR-9.4.7Clinical safety audit by Orthopaedic Surgeon advisor5
FR-9.4.8Production cert · stability proven8
TOTAL76 SP

6. 👥 Team Capacity

RoleAllocationFocus
Eng Lead / BE1.0 FTEX-ray AI + MSK pathways · HITL SLA · CPG
BE Dev 21.0 FTECross-module care plans · red-flag workflow
FE Dev1.0 FTEScreening UX · specialist HITL UX
Prompt Eng0.5 FTE4-culture Orthopaedics · Fracture AI + MSK Pathways prompt tuning
DevOps0.5 FTEHITL SLA monitoring · panel rota tooling
Founder0.7 FTEOrthopaedic Surgeon advisor coordination
Doc Zam0.4 FTEClinical oversight · cultural adaptation
Orthopaedic Surgeon Advisor (Datuk Dr Chandran Pillay)0.5 FTEClinical sign-off · audit · 4-culture review

7. 🔔 Sprint Ceremonies

  • Mon 9am — Sprint Planning + Advisor Intro (90 min)
  • Daily 9am — Standup
  • Fri (week 1) + Fri (week 2) 4pm — Mid-sprint demos
  • Wed (week 3) 2pm — CPG compliance walk (90 min)
  • Thu (week 3) 2pm — Clinical safety audit (3 hours)
  • Mon (week 4) 9am — Sprint Demo + Attestation (90 min)
  • Mon (week 4) 11am — Retro + next sprint plan (60 min)

8. 🩺 Sign-off Items

  • X-ray AI + MSK pathways validated · zero false-negative on test cases
  • Open fracture red-flag: zero missed escalation
  • Orthopaedic Surgeon HITL SLA met ≥ 95%
  • MOH CPG alignment verified
  • 4-culture prompt review clean
  • Cross-module care plans tested with ≥ 20 patients
  • External clinical safety audit clean
  • Production cert · ≥ 4-week stability proven

9. 🎬 Demo Schedule — 31 Mar 2030

TimeSegment
0-10v3.5 update · M20 narrative · why orthopaedics · fracture ai + msk pathways matters
10-25Live patient flow · X-ray AI + MSK pathways screening · severity stratification
25-40Open fracture red-flag · mandatory escalation · specialist HITL
40-55MOH CPG alignment · MOH-MY validated workflow walkthrough
55-70Cross-module care plans · composite chronic disease management
70-80Cultural prompts · 4 ASEAN contexts demo
80-90Orthopaedic Surgeon Advisor Datuk Dr Chandran Pillay keynote · clinical attestation

10. 🛡️ Contingency

RiskTriggerResponse
X-ray AI + MSK pathways false-negativeMissed red-flag in testConservative thresholds · mandatory dual-review
Specialist HITL SLA breachPanel rota gapsBackup panel · 24-hour escalation to Doc Zam
CPG misalignmentMOH-MY CPG update mid-sprintTrack CPG changes · iterative re-alignment
Cultural prompt rejectionAdvisor flags insensitivityPer-culture prompt overrides