👶 Sprint 7.1 · Paediatrics-Deep · M12 · 3 - 23 Jan 2028
← Hub ← Phase 7 SPRINT 7.1 · SPECIALTY M12 PAEDS

Sprint 7.1 · Paediatrics-Deep · M12

First specialty module. Weight-band dosing engine. WHO + MOH growth charts (height/weight/HC for age). Vaccination schedule (MOH 2027 immunisation programme). Paeds-specific CPG (asthma · fever · gastroenteritis · neonatal jaundice · febrile seizure). Paediatrician HITL queue. Children become first-class citizens.

1. 🎯 Sprint Summary

Sprint7.1 (M12 PAEDS · Paediatrics-Deep)
Duration3 - 23 Jan 2028 (3 weeks · 15 working days)
ModuleM12 PAEDS · first specialty
GoalWeight-band dosing · WHO+MOH growth charts · vaccination schedule · 5 paeds CPG · paediatrician HITL queue · 50 tenants total
Capacity5 FTE (2 BE + 1 FE + 1 prompt + 0.5 DevOps + 1 Onboarding) + 0.5 Founder + 0.5 Doc Zam + 0.5 paediatric advisor
Velocity target95 SP
Demo date23 Jan 2028

2. 🧩 Module Scope

  • Weight-Band Dosing: Age + weight + drug → safe dose calculation · 50+ paeds drugs · cap at adult dose · clinical advisor reviewed
  • WHO + MOH Growth Charts: Height-for-age · weight-for-age · BMI-for-age · head circumference · plotted live in encounter
  • Vaccination Schedule (MOH 2027): BCG · Hep B · DTP-Hib · OPV/IPV · MMR · JE · MOH National Immunisation Programme (NIP) auto-tracked
  • Paeds CPG Library: Asthma · Fever · Gastroenteritis · Neonatal jaundice · Febrile seizure · WHO + MOH guidelines
  • Paediatrician HITL Queue: Specialist override panel · pediatric-specific safety triggers · severity scoring
  • Pediatric Triage Adaptations: Age-aware thresholds · < 3mo special handling · sepsis detection (PEWS score) · febrile under-5 protocol
  • Parent-PA Integration: M1 Patient PA extends for parent-as-proxy · weight + age input · dosing calculator
  • Vaccination Reminder Engine: Auto-WhatsApp reminders for upcoming NIP vaccines · per-child schedule · MOH compliance reporting

3. 🚦 Pre-Sprint Gate Checklist

  • Phase 6 v1.3 closeout · 40 tenants stable · multi-region federation
  • Paediatric clinical advisor onboarded (4 weeks · MOH-recognised paediatrician)
  • Weight-band dose corpus seeded (BNF-c · DynaMed paeds · MOH paed formulary)
  • WHO growth chart data sets imported · MOH adapted curves
  • MOH 2027 NIP schema published · vaccine catalogue loaded
  • 5 paeds CPG documents indexed in pgvector
  • PEWS (Paediatric Early Warning Score) algorithm validated
  • Paediatrician HITL flow drafted (severity + age-aware criteria)
  • Test paediatric tenant clinic identified (3 paediatric-leaning clinics)

4. 📅 Day-by-Day Plan (15 days)

D1Mon 3 Jan · Schema + Dosing Engine
DB migrations · weight-band dosing engine · 50 drugs first batch.
D2Tue 4 Jan · WHO Growth Chart Component
FE: live percentile plot · 0-5y / 5-19y · interactive · M4 encounter integration.
D3Wed 5 Jan · MOH NIP Schedule + Vaccination Tracker
2027 schedule · per-child completion · catch-up logic · MOH reporting.
D4Thu 6 Jan · Paeds CPG Library + RAG
5 CPGs indexed · pgvector · CitationEnforcer specialty filter.
D5Fri 7 Jan · Mid-Demo + Paediatric Advisor Review
Live mid-demo · advisor reviews 5 mock paeds encounters · clinical accuracy.
D6Mon 10 Jan · PEWS + Pediatric Triage
PEWS scoring · age-aware triage thresholds · <3mo special handling.
D7Tue 11 Jan · Paediatrician HITL Queue
Specialist override panel · severity-driven · audit trail extension.
D8Wed 12 Jan · Parent-PA Integration
M1 extends for parent-as-proxy · weight + age · dosing calculator UI.
D9Thu 13 Jan · Vaccination Reminder Engine
Auto-WhatsApp · per-child schedule · MOH compliance reporting.
D10Fri 14 Jan · Mid-Demo Round 2
3 paeds tenant clinics flip on · live patient encounters reviewed.
D11Mon 17 Jan · Cross-Module Integration
M5 Pharmacy paeds dose check · M6 ADR paeds severity · M11 chronic care peds.
D12Tue 18 Jan · Specialty Filament Resource
Per-tenant paeds dashboard · vaccination compliance · growth chart trends.
D13Wed 19 Jan · Hardening + Production Test
Doc Zam tenant + 3 paed clinics flipped on production · 24h monitor.
D14Thu 20 Jan · Pen-Test Light + 50th Tenant
M12 surface tested · 50th tenant onboarded via wizard.
D15Fri 21 Jan · Demo Prep + Polish
Demo deck · 50-tenant milestone · paeds adoption metrics.
+Mon 23 Jan · Sprint Demo + Retro
9am demo · 11am retro · 2pm 7.2 (OG-Deep) prep.

5. 📦 Deliverables

FRItemSP
FR-12.1Schema + weight-band dose engine (50 drugs)8
FR-12.2WHO + MOH growth charts (live plot)8
FR-12.3MOH 2027 NIP vaccination schedule5
FR-12.45 paeds CPG library + RAG8
FR-12.5PEWS + pediatric triage adaptation8
FR-12.6Paediatrician HITL queue5
FR-12.7Parent-PA proxy integration (M1 extension)5
FR-12.8Vaccination reminder engine + MOH report5
FR-12.9M5/M6/M11 cross-module paeds integration8
FR-12.10Paeds Filament dashboard5
FR-12.11Production rollout · 3 paeds clinics + Doc Zam5
FR-12.12Paediatric advisor sign-off (50 sample)5
FR-12.13Pen-test light · M12 surface3
FR-12.1450th tenant onboarded5
FR-12.15Compliance pack update (paeds)3
TOTAL86 SP

6. 👥 Team Capacity

RoleAllocationFocus
Eng Lead / BE1.0 FTEDose engine · cross-module integration
BE Dev 21.0 FTENIP schedule · vaccination reminder · M9 audit ext
FE Dev1.0 FTEGrowth charts · paeds Filament · parent-PA UI
Prompt Eng1.0 FTEPaeds CPG corpus · age-aware triage
DevOps0.5 FTEWhatsApp infra · scale tuning
Onboarding Lead1.0 FTE3 paeds clinics + 50th tenant
Founder0.5 FTESpecialty advisor BD · M12 launch
Doc Zam0.5 FTECross-specialty oversight · clinical sign-off
Paediatric advisor0.5 FTE (heavy)50-sample review · HITL panel design · CPG validation

7. 🔔 Sprint Ceremonies

  • Mon 3 Jan 9am — Sprint Planning (90 min)
  • Daily 9am — Standup (15 min · paeds advisor joins Tue/Thu)
  • Fri 7 + Fri 14 Jan 4pm — Mid-sprint demos (60 min each)
  • Mon 10 Jan 4pm — Paeds advisor 50-sample review (3 hours)
  • Mon 23 Jan 9am — Sprint Demo (60 min)
  • Mon 23 Jan 11am — Sprint Retro (60 min)

8. 🩺 Sign-off Items

  • Weight-band dose accuracy ≥ 99% (50-sample BNF-c reference)
  • Growth chart percentile plot accurate vs WHO published values
  • MOH 2027 NIP schedule clinically correct (advisor verified)
  • 5 paeds CPGs RAG retrieval accurate ≥ 95% specialty queries
  • PEWS scoring matches advisor manual calc on 30 cases
  • Pediatrician HITL queue clinically appropriate (severity flagging)
  • Parent-PA proxy flow legally + clinically defensible
  • Vaccination reminder accuracy + MOH compliance report passes
  • Production rollout: 3 paeds clinics live · 0 P0 incidents
  • Final demo (23 Jan) — written sign-off · paediatric advisor + Doc Zam

9. 🎬 Demo Agenda — 23 Jan 9am (60 min)

TimeSegment
0-5v2.0 narrative · M12 first specialty · 50-tenant milestone
5-15Live paediatric encounter · 18mo child · weight-based dose · growth chart plotted
15-25Vaccination tracker · NIP schedule · WhatsApp reminder demo
25-35PEWS scoring on febrile child · paediatrician HITL queue trigger
35-45Parent-PA proxy session · weight input · safe dose calculator
45-55Cross-module: M5 paeds dose check · M6 ADR · M11 chronic asthma
55-60Doc Zam + paeds advisor sign-off · 7.2 (OG) prep

10. 🛡️ Contingency

RiskTriggerResponse
Paeds advisor unavailablePersonal/clinical conflictBackup advisor identified · slip 50-sample review by 1 week
Dose calc accuracy < 99%Audit failTighten engine · clinical advisor mandatory override · iterate before launch
NIP schema driftMOH 2027 update mid-sprintSchema versioning · backwards-compatible · production stays on locked version
Pediatric clinic onboarding slow< 2 of 3 by D14Phase exit at 2 paed clinics · 3rd in 7.2 stretch
Cross-module integration breaksM5/M6 paeds compatibilityFeature flag rollback · iterate post-launch